How many days for setting up the tents?
Before the installation, the builder need to know the details of the layout. Normally, the installation could be done within one day but it doesn't include measurement and transportation.
For large tents, it depends on whether pre-embedded foundation piles are needed. Generally, using ground stakes is faster than pre-embedding foundation piles, but the stability is slightly lower.
The following is the estimated time for setting up:
Gazebo Glass Wall Tents - 4 builders 2 hrs
https://www.highpeaktent.com/en/category/A0204.html
6M x 6M Glass Wall Tents (2020) - 4 builders 2~4hrs
https://www.highpeaktent.com/en/category/A0201.html
6M x 12M Glass Wall Tents (2040) - 6 builders 4~8hrs
https://www.highpeaktent.com/en/category/A0202.html
Large Lightweight Glass Wall Tent (2530) - 8 builders 2 days