How long does a tent installation usually take?
Small tent installations can generally be completed within one day (excluding site measurement, transportation, and other preparatory work). The installation time for larger tents depends on whether embedded anchors are required and on the structural configuration.
Prior to installation, site planning, ground conditions, and installation methods must be confirmed with the sales team to allow for proper manpower allocation and scheduling.
The following are estimated installation times for different tent types:
◆ Gazebo Glass Wall Tents - 4 builders 2 hrs
◆ 6M x 6M Glass Wall Tents - 4 builders 2~4hrs
◆ 6M x 12M Glass Wall Tents - 6 builders 4~8hrs
◆ Large Lightweight Glass Wall Tent - 8 builders 2 days